Pipelines
Coronado
Pipeline
Completed
Project Description: Approximately
18,000 linear feet (3.4 miles) of 30” pipeline that will begin
on Academy Road, proceed east on Academy to McKinney Drove, then turn
north on McKinney to Forest Hills Drive, then west on Forest Hills to
just east of the I-25 frontage road, then north to Del Rey Avenue, then
east on Del Rey to San Pedro Drive, then north on San Pedro to Palomas
Ave., then east on Palomas to the Coronado Reservoir.
Consultant: DMJM
Contractor: RMCI, Inc.
Construction Start Date (Estimated): April 2007
Construction End Date: August 2007
Major Streets Affected: Academy, Forest Hills Drive,
McKinney Drive, Louisiana, Osuna
|