San Juan Chama Drinking Water Project
 
free water bottle sample Click here for video, "Water for Generations to Come"
Click here for additional information about the Albuquerque Bernalillo County Water Utility Authority

Pipelines

Coronado PipelineCoronado Pipeline

Completed

Project Description: Approximately 18,000 linear feet (3.4 miles) of 30” pipeline that will begin on Academy Road, proceed east on Academy to McKinney Drove, then turn north on McKinney to Forest Hills Drive, then west on Forest Hills to just east of the I-25 frontage road, then north to Del Rey Avenue, then east on Del Rey to San Pedro Drive, then north on San Pedro to Palomas Ave., then east on Palomas to the Coronado Reservoir.

Consultant: DMJM 

Contractor: RMCI, Inc.

Construction Start Date (Estimated): April 2007

Construction End Date: August 2007

Major Streets Affected: Academy, Forest Hills Drive, McKinney Drive, Louisiana, Osuna