San Juan Chama Drinking Water Project
 
free water bottle sample Click here for video, "Water for Generations to Come"
Click here for additional information about the Albuquerque Bernalillo County Water Utility Authority

Pipelines

Raw Water Pipeline #1 from Diversion Dam
West Valley Pipeline

Completed

Project description: 72" diameter steel pipe and will extend for approximately 17,500 linear feet (3.3 miles) from the Rio Grande River to Paseo Del Norte/North Diversion Channel.

Consultant: Boyle Engineering

Contractor: Bradbury & Stamm/SJ Louis

Construction Start Date: November, 2005

Construction End Date: June, 2007

Major Streets Affected: Rio Grande, Edith, Fourth Street NW, BNSF Mainline Railroad Track, Second Street NW, Paseo del Norte.